Monday, January 26, 2009

Framing Day 4 & 5

Framers were off on Friday - a delay in getting the shipment to the site. Not to big of a deal.

They are still working at a very good clip - the entire first floor is pretty much done - today they started on the joists/lvls for the 2nd floor...having something above your head certainly gives it more sense of space.

This weeks weather looks pretty good - if you call below avg good - cold, but no snow except for a few passing flurries - temps in the low 20's. Hopefully, substantial progress is made - as hopefully, in two weeks or so, the roof will be on and we wont have to fret the weather anymore.


Lots of lumber - ceiling starting to go on 1st floor...


The back of the house - sans the 2nd floor...


Steel is set in the garage to support the rooms above it...