Ahh, if only we had started framing the other week when it was 60 degrees...now its 5 and miserable.
The framing - which was supposed to start on Monday got as far as takign some final measurements - and with the snow on Tue/Wed and now temps of 0-10, looks like this week is down the crapper. Framing is likely off until next week.
As you see on HGTV - and you never think it will be you - nobody finishes on time - I can now vouch for that. Between are little blueprint change, the framer being out of town for a week and now this week weather delay - likely 3 weeks off pace - which is about the amount of time it would take to have the framing done - which then we wont be impacted by weather as much.
Other than that, at a stand still this week. Will work on getting ahead in some of the other areas - but really just want to see some lumber going up. 10-day forecast shows dry conditions and a return to normal temps next week, so hopefully we make some progress.
I have monday off (MLK day), so may try to get with the kitchen designer to get us on pace there with our revisions. Every time we think we have it figured out, we deviate somewhere else.
Our project has now made the website of the service we are using...
http://ubuildit.com/resource-center/projectgallery/mokena-illinois/